Mostasmereen (220/66/11 KV) GIS Sub-station
Project Description
GE & Rowad are working as a consortium for 26 months for the procurement and installation of four independent substations located in Egypt.
Time frame for finishing Substation 220/66/11 KV in Mostasmereen is 8 months.
Energizing Substation 500/220 KV of Ismailya East is 20 months.
Substation 500/220 KV in Beni Suef will take 18 months to be completed. Substation 500/220 KV of Tamy El Amdeed will be finished within 19 months.