Continuing cooperating with international EPC contractors, RME has cooperated with Gamesa as their subcontractor for carrying out the civil works package of the NREA GULF El ZAYT wind farm (KfW Extension) project financed by NREA. The wind farm is composed by 20 GAMESA Wind turbines G80-2 MW tower 60 meters, with a total installed power of 40 MW located at Gulf El Zeit at around 4 km from Red Sea coast Highway, 5 km northwest of Ras Shukair, 120 km north of Hurghada, Egypt.

Scope of Work:

Civil Works for WTG Footings & WTG Platform.

New internal roads (Firm, base & Sub base) is created up to every wind turbine position.

Location: Gulf El Zeit, Egypt

Client: Gamesa

Owner: NREA

Contract Value: 25,269,551 EGP

 Project Duration: 6 months