GE & RME consortium are proofing a very significant progress in french funded substations project as it represents one of the urgent as well as important to the Egyptiam ministry of electricity. The project includes the EPC construction of Al. Mostasmereen Substation 220/66/11 KV, Ismailia Substation 500/220 KV, Beni Suef Substation 500/220 KV of Beni Suef & Tmai El. Amdeed Substation 500/220 KV.

 

Client:Egyptian Electricity Transmission Company (EETC)

Contract Value: 225,000,000 Euro

Project Duration: 20 months